Early action now on possible performance issues will “flatten the curve” of customer problems in the coming weeks and months.
Here are three things technology and software vendors can do right now to get ahead of problems that may appear (if they are not already) with services such as development, implementation and support:
Learn from IBM: Do what is required when there are failures of material assumptions.
In 2006, the State of Indiana signed a $1.3 billion contract with IBM to revamp the technology of the State’s welfare system. The economy went south in 2008. In the complicated breach of contract litigation that followed, IBM argued, among other things, that the economic downturn resulted in the failure of one of the material assumptions of the agreement. IBM urged the court to consider that failure of assumption when deciding whether IBM had materially breached its contract to develop and deploy the system.
The Indiana supreme court rejected IBM’s arguments. Why? Not because the economic downturn was not a failure of a material assumption. (It might have been.) Indeed, the contract specifically said that one of the parties’ material assumptions was that the economy would not take a downturn. But IBM did not do what the contract required in light of the downturn—it did not submit a change order request in response to the failure of the assumption, as the contract required.
Change orders anyway?
Even if your contract does not contain material assumptions, it may contain a procedure for procuring change orders. Parties include change order provisions so that they have an organized pathway for making changes to the scope, timing or pricing when circumstances—whether dramatic or trivial—change while the contract is being performed. Vendors should consider whether a simple change to the parties’ obligations can be made now to reduce bigger problems later. It is better for a ship to correct its course early in the journey rather than after many weary days at sea.
And from a practical, customer-focused perspective, the discussions around possible change orders give a vendor the opportunity to communicate with its customers. This gives the vendor the chance to assure the customer that services are safe in the long run, and can work to build trust and goodwill that will be key in the further development and collaboration that is going to happen in the technology space once this COVID-19 episode has come to a close.
Force majeure notice—it is critically important
In the litigation against the state of Indiana, IBM also claimed that severe flooding in the state in 2008 was a force majeure event that excused IBM’s performance. Again, as with the argument for the failure of material assumption, IBM did not do what it was required to do under the terms of the contract to avail itself of this excuse in performance.
The court found that force majeure did not apply because IBM did not give appropriate notice as required under the agreement. This highlights a critical takeaway—if a vendor sees an upcoming need to claim that it cannot perform due to some circumstance arising from causes outside its control, it is better to place the customer on notice of that fact sooner rather than later.
So, here are the key questions to ask right now:
Being proactive now, in the early stages of the COVID-19 crisis, will—just as in the epidemiological context—flatten the curve of problems later.
State of Indiana v. IBM Corp., 51 N.E.3d 150 (Ind. 2016)
Sponsored byRadix
Sponsored byCSC
Sponsored byIPv4.Global
Sponsored byWhoisXML API
Sponsored byDNIB.com
Sponsored byVerisign
Sponsored byVerisign
There also needs to be consideration of the recovery phase of such a major downturn as we have with COVID-19. Changes can be delayed that will have a future impact, upsetting synchronization and order of changes. When the order or sequence of delayed changes take place, things could fail in the future that would not, otherwise. An example is Firefox’s pending deprecation of TLS versions 1.0 and 1.1. They delayed the change due the need for people to get timely information, during this pandemic, without the delay of websites to upgrade their TLS infrastructure. An example of a website still running an older version of TLS is CircleID itself (running Apache 2.2.3 on Red Hat). Change orders need to consider material assumptions well into the future as others apply their own changes in now unexpected ways. I would expect issues from these terrible months to be raised in courts for decades.